Eight 58-ton crystallization machines were perfectly positioned for the Shandong Tianli Pharmaceutical project department

Release time:

2024-10-22


On August 25, 2024, an important lifting task was successfully completed at Shandong Tianli Pharmaceutical Co., Ltd. This time, 8 vertical crystallization machines with a diameter of 3.8m and a weight of 58 tons are to be lifted. The construction team has adopted a powerful configuration of a 500 ton main crane and an 80 ton sliding tail.

Before the lifting work officially begins, a large amount of preparation work is being carried out intensively. Professional technicians conducted a detailed survey and measurement of the construction site, accurately planning the lifting path and positioning of each equipment. They repeatedly calculate various data to ensure the scientificity and safety of the lifting plan.

Before the lifting began, the construction team conducted a comprehensive inspection and debugging of the 500 ton main crane and 80 ton tail, from the strength of the crane arm to the stability of the hydraulic system, from the sensitivity of the control system to the reliability of the safety device, every detail was not overlooked. At the same time, strict inspections were conducted on key lifting components such as steel wire ropes and lifting ears. Ensure that the steel wire rope is free from wear, breakage, and other issues, and that the strength and welding quality of the lifting ears meet the requirements.

Strict training and safety briefing were provided to the personnel involved in the lifting operation, clarifying each person's responsibilities and tasks. Everyone carefully studies the lifting plan and operating procedures, and is fully prepared for the upcoming challenges.

However, the plan cannot keep up with the changes. Due to conflicts with other units' working faces, the lifting work had to be carried out in two days. But this did not disrupt the pace of the construction team, who approached each lifting with a more rigorous attitude.

This excellent construction team demonstrated a high level of professionalism and tenacious fighting spirit at critical moments. They quickly adjusted their strategies and rearranged their work plans to ensure that the tasks could be completed smoothly. At the beginning of the first hoisting, everyone was fully focused and carried out the operation in an orderly manner according to the established plan. The 500 ton main crane demonstrated strong power, and the 80 ton tail slip cooperated seamlessly. One equipment after another was steadily lifted and gradually approached the predetermined position. Despite the scorching sun and sweat soaking their clothes, they did not back down. With everyone's joint efforts, the first phase of the lifting task was successfully completed.

During the interval, the construction team conducted another inspection and maintenance of the equipment and lifting tools to prepare for the second lifting. They carefully summarized the experience and lessons learned from the first hoisting and further optimized the plan. When the second lifting came, everyone still maintained a high level of focus and enthusiasm. In the end, all 8 devices were successfully hoisted into place.

The successful completion of this lifting task is inseparable from the meticulous preparation work in the early stage and the outstanding performance of the construction team. They are writing their own hoisting legend with sweat and wisdom. They have demonstrated excellent engineering quality and team spirit through practical actions, setting an example for the industry.