The melting furnace crown of the Phase I technical transformation project of Chenzhou Kibing has been successfully locked

Release time:

2026-11-25


On November 18, 2026, the crown of the Phase I technical transformation project of Chenzhou Kibing was successfully closed, marking that the main works of the Phase I technical transformation melting furnace have progressed by more than half and that the project construction has achieved phased results.

This cold repair technical transformation is a four-line calendered glass production line with one furnace, featuring a large amount of structural modification, high masonry precision requirements, and intensive cross-operation. To ensure the schedule is met as planned, the project department worked out a reverse schedule around the main masonry line, decomposed the targets down to disciplines, work teams, and shifts, and tracked and corrected deviations day by day. In response to situations such as delays in civil works and untimely delivery of bricks, the project department took the initiative to coordinate, learned in advance the inbound plan of owner-supplied materials, dynamically adjusted the processes, and ensured that work commenced immediately upon handover of the work face and masonry began immediately upon material arrival, minimizing waiting and idle time to the greatest extent.

During construction, the project department adhered to the principle of "safety first, quality foremost, and schedule prioritized," reviewed and accepted each item against design drawings and industry standards, and implemented the practice of "masonry one layer, inspect one layer, confirm one layer" to ensure that the masonry quality meets design standards and process requirements. At the same time, it strengthened safety control for work at heights, edge protection, and cross-operations, achieving full control of the construction process and first-time excellence in work quality, ultimately earning recognition from the owner.

Next, the project department will keep its focus on the goal of ignition on schedule, advance subsequent work with stricter standards and measures, and ensure that the project is completed and put into operation on time, with high quality, and efficiently, laying a foundation for long-term cooperation between both parties.