Successful grid connection of Unit # 9 of Indonesia Delong (4 × 330MW) unit project by commissioning company

Release time:

2024-03-12


Commissioning company Indonesia Delong (4×330MW) unit project Unit #9 set a speed of 3000r/min at 0:41 am on February 20, 2024, laying a good foundation for subsequent units to be connected to the grid for power generation. This unit is the product of 1970s, the original data is missing. The on-site personnel worked hard together for five days and four nights, and after various parameter adjustment and exploration, the turbine generator set successfully rushed and fixed speed. The unit of this project is the whole set of sub-system debugging of the first 330MW capacity unit independently completed by our company, and has accumulated valuable experience for the subsequent commissioning of large units.