The hydrostatic test for Boiler No. 1 at the Gongyi Eco-Industrial Park Waste-to-Energy Project was successfully completed
Release time:
2025-08-22
At 11:58 on August 5, 2025, the Gongyi Waste-to-Energy Project, part of the city's eco-industrial park, achieved a significant milestone: the hydrostatic test for Boiler No. 1 was successfully completed. During the test, the boiler maintained a stable overpressure of 9.0 MPa for 20 minutes, with all systems operating smoothly and meeting design specifications, marking a critical breakthrough in the project.
Since its commencement on March 1, 2025, the Gongyi project has faced multiple challenges, including tight budgets, delayed equipment deliveries, and complex construction conditions. Through scientific planning and precise execution, the project team dynamically adjusted construction schedules and optimized the allocation of human and material resources. All personnel involved tackled difficulties head-on, overcoming issues such as limited working space and equipment defects, ultimately ensuring the timely completion of this crucial milestone.
The success of the hydrostatic test not only paves the way for subsequent steps including furnace lining, insulation, boiler drying, and purging but also signifies that the Gongyi waste incineration power generation project has officially entered the equipment installation and commissioning phase. This progress is of great significance for advancing the safe and resource-efficient treatment of local household waste.

Key words: