Indonesia Morowali Industrial Park Project successfully passed 168h full load commissioning.

Page view
[Abstract]:
Commissioning company Indonesia Qingshan Eternal Smelting Co., Ltd. 350MW thermal construction power generation project #2 unit successfully passed the 168h full load commissioning test on May 16.

Following a successful grid connection on May 1, the #2 unit of 350MW thermal construction power generation project of Indonesia Qingshan Eternal Smelting Co., Ltd. of the commissioning company passed the 168h full-load test run assessment on May 16, the whole process was smooth, and has now been handed over to the Party-A smoothly.