On July 25, the 1# boiler hydraulic test of Yichuan County Waste Incineration Power Generation Project was successful. At 13:10 on July 25, the 1# boiler was pressured to 9.125MPa, and the experts of the Boiler Inspection Institute started physical inspection. The pressure was maintained for 20 minutes. At 13:30, the pressure was normal and then the pressure began to be released. This means that the 1# boiler passed the final acceptance smoothly. Subsequently, the representatives from the owner company, the supervisor company and the Boiler Inspection Institute signed the boiler hydraulic pressure test qualification list.