The municipal solid waste incineration power generation project in Longquan city has successfully passed the 168-hour trial operation.

Release time:

2020-11-03


At 16:00 on October 23, 2020, the Longquan Municipal Solid Waste Incineration Power Generation Project successfully passed the 168-hour trial operation.

 

At the beginning of July 2020, the commissioning personnel entered the site gradually, and carried out a comprehensive investigation of the various systems of the unit. The problems and unreasonable items found were timely rectified, which created the conditions for the first start of the unit. The unit was successfully connected to the grid for the first time on August 14 and restarted on October 14 to successfully complete the 168-hour trial operation on the 23rd.