In the rush period, Party A’s needs should promote the development of the company’s spirit ——Shandong Union Chemical Project Department 2019 Spring

Page view
[Abstract]:
Recently, the first branch of the Shandong Union Chemical Project Department raced against time, rushed to the construction period, and strived to meet the needs of Party A and complete the work as scheduled

Recently, the first branch of the Shandong Union Chemical Project Department raced against time, rushed to the construction period, and strived to meet the needs of Party A and complete the work as scheduled.

At present, the project department has more than 340 people on site, including all the workers, including the management staff. Every Monday to Saturday, they work overtime until 9:00 pm, and only have a normal rest on Sunday. In order to save time on the way to and from work, workers will bring tableware when they go to the construction site in the morning. At lunch time, the canteen will send lunch to the construction site. The workers will eat in the open space on the spot. After a meal, they will continue to invest in “battle”.

The project department is so hard to meet the schedule of Party A. A few days ago, Party A issued the task of testing the whole plant on May 28th. The project department undertook the pipeline installation of the transformation, desalinated water, sulfur recovery, sulfuric acid storage and waste heat power generation, and the pipe network of the plant. The length is long, the number of pipes is basically more than 150,000 inches, the installation height is basically above 7 meters, the thickest pipe thickness is 45mm, the pipeline has invested more than 140 people, and there are nearly 100 people now. Work hard on each section. In addition to the pipeline, the project department also undertook 15 million yuan of electrical installation work.

The reason why Party A can hand over such a heavy burden to the project department is that the project department gave Party A enough confidence. In 2018, due to the low price, strict construction quality requirements, tight schedule, etc., some construction units could not keep up with Party A's rhythm and exited halfway. At first, Party A was also skeptical about the new factory. However, with the careful organization, reasonable arrangement, and concerted efforts of the project department, the steel network structure, transformation equipment and pipelines were completed in a timely and excellent manner. And the construction of coal-fired electrical and other sections, which changed the view of Party A on us and recognized the construction progress and quality of the project department.

Spring blossoms and long grasses fly, it is a season of relaxation and enjoyment of life. However, for the Union Chemicals Project Department, it is a day to deal with heavy work and “shoulders to cheer up”. They are at home and they pay A group of friends and expanding one market, they integrate the company culture into the blood. For Party A's planning, for the development of Henan installation, they will continue to struggle in the future!

 